312 West Franklin Avenue
Pomona approved an 11-unit condominium project at 312 West Franklin Avenue in 2022. After two time extensions, the City Council approved its final tract map in July 2026. The lot has been cleared, but a building permit hasn't shown up in public records yet.
Units
11
Site area
About 0.55 acres
Details
- Address
- 312 West Franklin Avenue, Pomona, CA
- Case number
- DPR-18140-2022 / TRACTMAP-18440-2022
- APN
- 8344-021-005
- Buildings
- Four three-story buildings (Type V-B construction)
- Unit mix
- 11 three-bedroom condominiums, about 1,449 sq ft each (15,939 sq ft livable total)
- Parking
- 22 covered spaces (two per home); one 26-foot driveway from Franklin Avenue
- Applicant
- Franklin 9, Inc.
- Resolutions
- PC Resolutions 22-032 & 22-033 (Dec 14, 2022); City Council Resolution No. 2026-78 (July 6, 2026: Final Tract Map TM 83563)
- Entitlements
- DPR-18140-2022 + TRACTMAP-18440-2022 (approved 2022); EXT-001787-2024 (first extension, 2025); EXT-000704-2025 (second and final extension, 2026); Final Tract Map TM 83563 (City Council, July 2026); DHS-000508-2025 (historic determination, 2025)
- Site history
- A 2025 historic determination (DHS-000508-2025) found the existing structures did not have enough historic significance to qualify for protection; they were demolished in November 2025
- CEQA
- Class 32 categorical exemption (in-fill development)
Pomona approved an 11-unit condominium project at 312 West Franklin Avenue in 2022. After two time extensions, the City Council approved its final tract map in July 2026. The lot has been cleared, but a building permit hasn't shown up in public records yet.
What's proposed
The project is 11 three-bedroom condos in four three-story buildings on a little over half an acre. Each home is about 1,450 square feet with two covered parking spaces. Cars use a single driveway off Franklin Avenue, and a homeowners association will look after the shared areas. The Planning Commission approved the project in 2022, and the plans haven't changed since.
Creative Design Associates (CDA+PDG) in the City of Industry drew the plans. Cal Land Engineering of Brea did the civil engineering. Gouvis Engineering of Irvine did the structural engineering and the mechanical, electrical and plumbing design. Emerald Design of Fullerton did the landscape plan. The full plan set is attached to the March 2026 Planning Commission staff report.
What it's replacing
An older building stood on the lot. A 2025 historic review found it didn't have enough historic character to qualify for protection, so it could come down.
How it got here
In California, an approval like this one expires if the project doesn't move forward in time. This one got two extensions from the Planning Commission, one in 2025 and a second, final one in 2026. In July 2026 the City Council approved the final tract map, which records the condo lots. City staff wrote that the map lets the landowner move toward finishing construction and getting the units ready to occupy.
Where it stands
The old building came down in late 2025, and the grading permit was pulled that December. As of late November 2026, we couldn't find a building permit for the condos in public records.
What this means if you live nearby
The approvals are done, the lot is cleared, and the final map is in place. The next public sign of progress would be a building permit, then work on the site.
Timeline
- Approved
Planning Commission approves the original 11-unit project
The Planning Commission approved Development Plan Review DPR-18140-2022 and Tentative Tract Map TRACTMAP-18440-2022 (Resolutions 22-032 and 22-033).
Source: pomona.legistar.com - Approved
Planning Commission grants a first time extension
The Planning Commission retroactively approved EXT-001787-2024, extending the 2022 approvals to December 14, 2025.
Source: pomona.legistar.com - Approved
Historic Preservation Commission takes up a historic determination
The Historic Preservation Commission's agenda carried DHS-000508-2025, a historic determination for the existing structures. Staff found they have little to no historic significance and recommended approval.
Source: pomona.legistar.com - Approved
Grading permit pulled after demolition
A January 14, 2026 letter from the project's general contractor to Pomona Planning says the existing structure was demolished in November 2025 and the grading permit was pulled December 16, 2025. A grading permit is not a building permit.
Source: pomona.legistar.com - Approved
Planning Commission grants the second and final extension
On its consent calendar, the Planning Commission approved EXT-000704-2025, a one-year extension of the 2022 approvals to December 14, 2026, under the original conditions.
Source: pomona.legistar.com - Approved
City Council approves the Final Tract Map
The City Council approved Final Tract Map TM 83563 (Resolution No. 2026-78) for the three-story, 11-unit condominium project. The staff report says the map lets the landowner move toward finishing construction and getting certificates of occupancy.
Source: pomona.legistar.com
Team
Source (staff-report): pomona.legistar.com ↗ · retrieved · last verified
Plan set: pomona.legistar.com ↗
More in Pomona
All Pomona developments (2)Advisory Desk
Own property in Pomona?
Get a preliminary read on what your lot can hold — zoning, density, and feasibility, grounded in local land-use data. No obligation, no sales pitch.